The Department of Rail Transport says the 132 km Maboke–Chira double-track project's Muak Lek elevated section is expected to finish in October 2027 (15-month build from August 2026). Until then, trains run single-track from Khlong Khanan Chit through the old line toward Nakhon Ratchasima, because Contract 2 (69 km) has not started construction and the Lam Takhong tunnel is still closed. Contract 1 is 96.52% complete and Contract 3 tunnels are finished. For a Thai SME, this is background: rail freight and passenger capacity on the northeast line will improve in the longer term, and nearby logistics or tourism businesses may want to plan around it, but no action is needed now.