EGAT plans to expand floating solar on dam reservoirs from 2,700 MW to 10,000 MW and extend some gas plants due to retire in 6-7 years, because data centres are pushing up power demand. Reserve margins are expected to fall to 15-20% next year. Gas turbines have about a 5-year delivery wait and roughly 7 years to build new capacity. For a typical SME this is background: the PDP2026 plan is still under review and the shift to 60-70% renewables is long-term, so no action is needed now. Watch for future electricity tariff and grid-related decisions.